When the City is notified of an existing pothole by residents, our Maintenance Division inspects the site and provides a temporary repair within 48 hours of the complaint.  The Maintenance Division will make a temporary repair using a high strength temporary patch material.  The location then gets added to the City's Pothole Repair Project list.  The Engineering Division puts together a pothole repair project twice a year, typically in the late winter and again in early fall.

​As part of the 2019 Pothole Repair Project, the City Contractor began the repair of 23,600 square feet of critical pavement potholes.  Work began at the end of February and is expected to be completed in March.